24/7 on call

A bathroom renovation timeline has two parts: preparation and work on site. Preparation, including planning, choosing fixtures, quotes, any approvals and delivery times, often takes longer than the building work itself. On site, a complete renovation of a typical bathroom involves demolition, plumbing and electrical rough-in, waterproofing, tiling, installing fixtures and finishing, with several trades working one after the other. Drying times for screed and waterproofing are part of the schedule. Good coordination, early ordering of fixtures and a clear plan are the best ways to avoid delays.

Phase 1: planning

  • Define what you want: layout, shower or bath, storage, lighting.
  • Check what is behind the walls: pipe condition, drainage, ventilation.
  • Choose fixtures, tiles and fittings.
  • Get quotes and agree on a schedule.
  • Clarify approvals: condominium, landlord, building permit for larger changes.

Our article on renovating a bathroom covers the planning questions in more detail.

Phase 2: ordering

Some fixtures, special tiles or made-to-measure shower screens have delivery times of several weeks. Order early so they arrive before they are needed. Starting demolition before the materials are confirmed is the most common cause of long interruptions.

Phase 3: work on site

Step What happens
Protection and demolition Protect adjacent rooms, remove fixtures, tiles and old pipes
Plumbing rough-in New supply and drain pipes, installation frames for wall-hung fixtures
Electrical rough-in Lighting, sockets, extractor fan, underfloor heating if planned and permitted (electric heating must comply with the RUEn)
Walls and floor Plaster, screed, levelling; drying time
Waterproofing Sealing in wet areas; drying time
Tiling Walls and floor, grouting
Fixtures WC, washbasin, shower, taps, accessories
Finishing Silicone joints, painting, final cleaning, handover

Drying times

Screed, plaster and waterproofing need time to dry before the next layer goes on. Rushing these steps causes problems later: cracked tiles, failing joints or moisture under the waterproofing. The product data sheets specify the drying times. A good schedule includes them from the start.

Living without a bathroom

If the home has only one bathroom, plan for the time without a working toilet or shower. Options include staying with family, a hotel for part of the time, or a temporary WC installed by the plumber. In some projects, the WC can be reconnected provisionally between phases. Discuss this with the contractor in advance.

What causes delays

  • Late fixture deliveries.
  • Hidden surprises: rotten pipes, damaged subfloor. Asbestos in buildings constructed before 1990 should be checked before work starts, not discovered during demolition.
  • Changes of plan during the work.
  • Trades not available when needed.
  • Missing approvals.

Partial renovation

Replacing only the fixtures or the shower is much faster than a full renovation. If pipes and tiles are in good condition, a partial renovation can be completed in a few days. Ask the plumber to check the condition of hidden pipes before deciding.

Example: bathroom in Locarno

A family renovates the only bathroom in their apartment. Fixtures and tiles are chosen and ordered six weeks in advance. Demolition reveals old galvanised pipes, which are replaced as planned. A temporary WC is installed for the critical days, and the family stays with relatives for the tiling and drying phase. The schedule holds because all materials are on site in time.

A sample sequence

  1. Weeks before: final design, quotes, orders, approvals.
  2. Start of works: protection, demolition, removal of rubble.
  3. Rough-in: plumber and electrician, often in parallel.
  4. Surfaces: plaster, screed and waterproofing, with drying times.
  5. Tiling: walls first, then floor.
  6. Fixtures: plumber returns to install WC, basin, shower and taps.
  7. Finishing: silicone, painting, accessories, cleaning, handover and checks.

Each step depends on the previous one. If one trade is delayed, the others move too. That is why a single coordinator is so useful.

Condominiums and neighbours

In apartment buildings, demolition and drilling are noisy. Most buildings have rules on working hours, and neighbours appreciate advance notice. The building manager may need to be informed, especially if water must be shut off for the whole building during pipe connections. Plan these moments carefully and announce them in time.

Common mistakes

  • Starting demolition before materials are confirmed.
  • Underestimating drying times.
  • Changing the layout during the work.
  • Forgetting the condominium’s rules on noise and working hours.

Buildings constructed before 1990: asbestos and hazardous substances

Before demolition, chasing, core drilling or any work on materials in a building constructed before 1990, the possible presence of hazardous substances, including asbestos, must be checked (for example in tile adhesives, plaster, fillers, floor coverings or pipe insulation). These checks come before the work starts; asbestos is not just a surprise to handle on site. If materials are suspected, work stops and the required procedure is followed with recognised specialists, as Suva requires.

Frequently asked questions

Can a bathroom renovation be done in a week?

A small partial renovation, possibly. A full renovation with new pipes, waterproofing and tiling usually takes longer.

Who coordinates the trades?

Ideally one contractor who coordinates plumbing, electrics, tiling and finishing.

When is the best time of year?

Any time, but avoid periods when you need the bathroom for guests or holidays.

Bathroom renovations in Ticino

AcquaKlima Sagl plans and carries out bathroom renovations with coordinated trades across Ticino. Learn more about plumbing and bathroom renovation or get in touch.

From the blog

Need a quote or a call-out?

Call us or message us on WhatsApp: we reply in Italian, French, German and English.